HomeBuyers guide › Site costs
Budget and scope guide · Ireland

What sits outside the modular-home price?

A factory quotation can be precise and still be far from the cost of a finished Irish home. Use this guide to expose foundations, groundworks, delivery, services and professional work before signing.

The useful priceCompare a complete route to a habitable, certified home—not a module at the factory gate. Put an owner, specification and price status beside every line item.

Factory price is not project price

“Turnkey” has no fixed legal scope. One supplier may include foundations, connections and finishes; another may mean only a finished module placed on a prepared base.

Ask for a written inclusions schedule and a matching exclusions schedule. Labels such as turnkey, shell, complete or ready to live in are less useful than a responsibility matrix that says exactly who designs, supplies, installs, tests and certifies each element.

Avoid an early headline figure. Site conditions and specifications vary too much for a credible universal cost per square metre. Build the budget from verified project packages and keep unknown items as visible allowances.

Foundation design is site-specific

A concrete slab, strip or ring-beam foundation, ground beams or piles can all be appropriate in the right circumstances. The choice is not a product-menu decision: it follows from the ground, levels, drainage, radon strategy and structural reactions from the building.

Information the engineer needs

  • Ground investigation and site levels.
  • Exact module weights, point loads, hold-down forces and connection details.
  • Final openings and module arrangement—not a generic brochure model.
  • Drainage, service entries, insulation, airtightness and radon details.
  • Proposed finished-floor level and flood or surface-water constraints.
  • Installation tolerances and the supplier's bearing and fixing requirements.

Make one party responsible for coordinating the foundation-to-module interface. A factory drawing marked “by others” and a local foundation quote based on assumptions can leave the most important junction undesigned.

The site-work packages people miss

PackageQuestions to priceCommon uncertainty
Surveys and investigationTopographic survey, ground testing, boundaries, services and levelsGround risk priced before investigation
Clearance and earthworksDemolition, excavation, fill, retaining, disposal and temporary accessWhat happens if unsuitable material is found?
Foundation and substructureDesign, concrete, reinforcement, insulation, radon, drainage and fixingsWhether supplier loads and tolerances are included
Delivery and liftingRoute survey, permits, escorts, crane, rigging, lift plan and weather delayCrane reach and road or overhead-line restrictions
Module assemblyWeather sealing, structural joins, roof closure, testing and making goodResponsibility where modules meet
UtilitiesElectricity, water, telecoms, metering, trenches and connection chargesDistance and network capacity
Drainage/wastewaterPublic connection or site assessment, treatment system and percolation areaWhether the site can support the proposed system
External completionSteps, ramps, paths, driveway, landscaping, boundaries and surface waterPlanning conditions and accessibility details
Professional/statutory workDesigners, engineer, energy work, planning, Building Control and certificationWho inspects factory work and concealed elements

Delivery needs a route and lift plan

The final kilometre can control the module dimensions and installation method. A preliminary review should consider bridge and road limits, bends, gradients, gate width, trees, overhead cables, parking restrictions, neighbouring land and space for both crane and delivery vehicle.

Crane cost depends on more than the module weight. Reach, setup area, ground bearing pressure, obstructions, rigging and the lift sequence matter. The crane contractor needs verified data; a satellite-image guess is not a lift plan.

Contract question: if delivery is aborted because the route or crane setup is unsuitable, who pays for storage, return transport, another crane and factory waiting time?

Services and wastewater can change feasibility

Confirm electricity, water, drainage and communications before ordering. A nearby cable or pipe does not prove that a connection or adequate capacity is available. Obtain site-specific information from the relevant utility or competent designer.

Where public wastewater is unavailable, the EPA says a new-house planning application must demonstrate that the site is suitable for a septic tank or other domestic wastewater treatment system. That can affect layout, usable garden area and the decision to proceed.

Build a responsibility-and-cost worksheet

Line itemResponsible partyPrice statusEvidence/date
House design and factory packageNamed supplier/designerFixed / allowance / excludedDrawing and quotation revision
Ground and foundationNamed engineer/contractorFixed / provisionalInvestigation and design revision
Transport, crane and installationNamed logistics leadFixed / route-dependentRoute and lift-plan revision
Utilities and wastewaterNamed designer/contractorConfirmed / estimateUtility or site-assessment evidence
Compliance and completionNamed project professionalsAppointment/fee agreedScope and inspection plan
ContingencyOwnerRing-fencedRisk register review

Update this sheet whenever the design, site information or supplier scope changes. Do not let a provisional sum silently become a fixed-budget assumption.

Quote red flags

Undefined “turnkey”

No room-by-room specification or list of excluded site work.

Foundation by others

No loads, tolerance, fixing or interface-design responsibility.

Delivery included

No surveyed route, crane reach or failed-delivery terms.

Services nearby

No written connection route, capacity or charge.

Certification extra

No named Irish design team or factory-inspection plan.

One total, no schedule

Deposits and stages do not correspond to measurable deliverables.

Frequently asked questions

Is a modular foundation cheaper than a conventional foundation?

It may be simpler for a particular lightweight system, but the answer depends on loads, ground, access, drainage and specification. Compare engineered solutions for the same site rather than generic claims.

Should I get a ground investigation before choosing a model?

Obtain professional advice on the appropriate investigation early. Ground information helps avoid selecting a system or budget that depends on unsupported assumptions.

Does a quoted crane price include road closure or traffic management?

Not necessarily. Ask whether permits, escorts, traffic management, rigging, setup, weather delay and a second attempt are included.

Can the supplier arrange everything?

Yes, if the contract truly gives one party responsibility and the necessary competent team. Verify the detailed scope and the Irish planning, design and Building Control roles rather than relying on the label “one-stop shop”.

Official sources

Reviewed: 6 August 2026. General budgeting information, not an estimate, foundation design or professional advice. Prices and feasibility depend on the exact site, design and contracts.